How much of the Sprint Backlog must be defined during the Sprint Planning event?

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

How much of the Sprint Backlog must be defined during the Sprint Planning event?

Post by answerhappygod »

How much of the Sprint Backlog must be defined during the Sprint Planning event?

A. Just enough tasks for the Scrum Master to be confident in the Development Team's understanding of the Sprint.
B. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
C. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
D. Just enough to understand design and architectural implications.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply