The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to

Post by answerhappygod »

The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?

A. Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog.
B. Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.
C. Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply