According to ACR, The NADCA Standard, it is recommended that the work plan include the name and contact information for:
A. the manufacturer of all equipment to be used on the project.
B. contractors and representatives involved in the project.
C. all employees working on the project.
D. past projects conducted by the company.
According to ACR, The NADCA Standard, it is recommended that the work plan include the name and contact information for:
-
- Site Admin
- Posts: 899559
- Joined: Mon Aug 02, 2021 8:13 am