Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk ev

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk ev

Post by answerhappygod »

Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule.
Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

A. She can have the project team pad their time estimates to alleviate delays in the project schedule.
B. She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
C. She can filter all risks based on their affect on schedule versus other project objectives.
D. She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply