You manage a project by using Project Professional 2013.A critical task is out of scope for the project. The stakeholder

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You manage a project by using Project Professional 2013.A critical task is out of scope for the project. The stakeholder

Post by answerhappygod »

You manage a project by using Project Professional 2013.A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.You need to implement a solution to meet the stakeholder's request.What should you do?

A. Click on the task, and click Inactivate.
B. Move the task to after the ending date for the project.
C. Delete the task from the schedule.
D. Click the Unlink Task button to unlink the predecessors and successors for the task.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply