Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are a project manager for a large telecommunications company that uses ProjectProfessional 2013.The project you have

Post by answerhappygod »

You are a project manager for a large telecommunications company that uses ProjectProfessional 2013.The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.What should you do?

A. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Start.
B. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Prorated.
C. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to End.
D. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 1. Change Fixed Cost Accrual to Start.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply