You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar a

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar a

Post by answerhappygod »

You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?

A. Remove the night calendar from the task and re-assign the resource.
B. Change the task mode to Manually Scheduled.
C. Change the task type to Fixed Units, Effort Driven, and then re-assign the resource.
D. Select scheduling ignores resource calendars for the task.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply