You are elected as the project manager of GHT project. You are in project initialization phase and are busy in defining requirements for your project. While defining requirements you are describing how users will interact with a system. Which of the following requirements are you defining here?
A. Technical requirement
B. Project requirement
C. Functional requirement
D. Business requirement