You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request.Where should the declined change request be documented and stored?
A. Change request log
B. Project archives
C. Lessons learned
D. Project document updates
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associat
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associat
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!