Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

An organization has a standardized change management plan that all project managers must adhere to. A project manager ha

Post by answerhappygod »

An organization has a standardized change management plan that all project managers must adhere to. A project manager has worked with the Change Control
Board in his organization to approve a change to project scope. What should the standardized change management plan require the project manager to do with the approved scope change?

A. Perform risk assessment on the new change.
B. Communicate the change to the vendor.
C. Create a cost estimate for the change.
D. Update the WBS.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply