A company uses its own private cloud, which has few available resources. Mission-critical systems and other information systems are running on it. A new system will be deployed on the private cloud. The following tests are included in the test plan:
✑ Load test (2h)
✑ Backup/restore test (6h)
✑ Functional test (8h)
✑ Failover test (1h)
The work schedule of the existing system is shown below.
To minimize the effect to the existing system, which of the following schedules is MOST suitable for the load test?
A. 02:00-04:00
B. 09:00-12:00
C. 18:00-20:00
D. 22:00-00:00
A company uses its own private cloud, which has few available resources. Mission-critical systems and other information
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A company uses its own private cloud, which has few available resources. Mission-critical systems and other information
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!