A technician is working on a virtual server migration project. The technician has already completed the SOW; however, th

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A technician is working on a virtual server migration project. The technician has already completed the SOW; however, th

Post by answerhappygod »

A technician is working on a virtual server migration project. The technician has already completed the SOW; however, the servers will not work without a critical network configuration that was missed in the original SOW. The technician needs to make the adjustments quickly.
Which of the following best practice processes should the technician perform NEXT?

A. Obtain end-user acceptance for the proposed changes and submit a change plan for additional work.
B. Submit the changes to the change board for approval.
C. Notify the change team of the changes needed and perform the changes.
D. Escalate to stakeholders and obtain override approval for out-of-scope changes.
E. Document the changes and perform the work.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply