Q3. Consider the following project. Draw the project network, determine the time to complete the project and critical pa
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Q3. Consider the following project. Draw the project network, determine the time to complete the project and critical pa
Q3. Consider the following project. Draw the project network, determine the time to complete the project and critical path. Complete the following table for activities E, F and I. Use the AOA method. (6 + 3 + 6 = 15 marks) Activity Predecessors A B С A D B E B F B G C,D H E I F J GH K I Time (weeks) 6 4 2 9 10 12 9 Town 8 15 9 Act. Dur. ES LS EF LF TF FF Arc ij E F I