If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
-