Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

ABC company needs 50,000 U /year , each order costs the company 180 $ , while each unit costs 3 $ to be hold . Now , the

Post by answerhappygod »

ABC company needs 50,000 U /year , each order costs the company
180 $ , while each unit costs 3 $ to be hold . Now , the company
used to place two orders /year , but they think to change this
policy to one of the following options : A: applying the EOQ B:
establishing a production line with a capacity of 350 U/ day
Conduct a total comparison between the three options and recommend
one of them .