The budget at completion for your project is $200,000. Your project's earned value is $125,000, while actual cost is $15

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The budget at completion for your project is $200,000. Your project's earned value is $125,000, while actual cost is $15

Post by answerhappygod »

The budget at completion for your project is $200,000. Yourproject's earned value is $125,000, while actual cost is $150,000.For the remainder of the project, you expect the same CPI. What isthe estimate at completion?
Group of answer choices
a. $220,000
b. $240,000
c. $210,000
d. $250,000