Question 11 pts Splitting large jobs into smaller jobs is a way to reduce scheduling difficulties. Group of answer choic

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Question 11 pts Splitting large jobs into smaller jobs is a way to reduce scheduling difficulties. Group of answer choic

Post by answerhappygod »

Question 11 pts
Splitting large jobs into smaller jobs is a way to reducescheduling difficulties.
Group of answer choices
True
False
Flag question: Question 2
Question 21 pts
Phantom bills are bills of material for "kits" of inexpensiveitems such as washers, nuts, and bolts.
Group of answer choices
True
False
Flag question: Question 3
Question 31 pts
The lot-for-lot lot-sizing technique is particularly appropriatewhen demand is not very smooth and set up cost is small compared toholding cost.
Group of answer choices
True
False
Flag question: Question 4
Question 41 pts
The master production schedule is a forecast of demand forfamilies of products.
Group of answer choices
True
False
Flag question: Question 5
Question 51 pts
Earliest due date sequencing rule always outperforms otherrules.
Group of answer choices
True
False
Flag question: Question 6
Question 61 pts
The work center master file contains data such as capacity andefficiency.
Group of answer choices
True
False
Flag question: Question 7
Question 71 pts
Taguchi quality loss function states that further deviation fromyour target value means higher losses financially.
Group of answer choices
True
False
Flag question: Question 8
Question 81 pts
Customer relationship management functions were designed intooriginal MRP systems, but they are no longer components of ERPsystems.
Group of answer choices
True
False
Flag question: Question 9
Question 91 pts
Customer satisfaction is the only objective of product/servicedesigns.
Group of answer choices
True
False
Flag question: Question 10
Question 101 pts
MRP is generally practiced on items with dependent demand.
Group of answer choices
True
False
Flag question: Question 11
Question 111 pts
Reduced inventory levels and faster response to market changesare both benefits of MRP.
Group of answer choices
True
False
Flag question: Question 12
Question 121 pts
One criterion for developing effective schedules is minimizingcompletion time.
Group of answer choices
True
False
Flag question: Question 13
Question 131 pts
First come first serve is a rule that is perceived as fair bycustomers.
Group of answer choices
True
False
Flag question: Question 14
Question 141 pts
Gantt charts are generally defined as a sequencing tool.
Group of answer choices
True
False
Flag question: Question 15
Question 151 pts
If X consists of one A and one B, and each A consists of one Fand two Gs, then A is the "parent" component of G.
Group of answer choices
True
False
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!