Ramandeep has completed the baseline schedule and the project has started as planned. Ramandeep uses MS Project to track
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Ramandeep has completed the baseline schedule and the project has started as planned. Ramandeep uses MS Project to track
Ramandeep has completed the baseline schedule and the project has started as planned. Ramandeep uses MS Project to track and monitor the schedule and to understand how activity changes can have an overall impact on the project schedule. Which tool is primarily being used to control the project schedule? a. Sensitivity Analysis O b. Scheduling Tool O c. Crashing O d. Resource Leveling Oe. What-if Analysis