QUESTION 4 The initial cash outlay for project A is RM12,000. Project A's discount rate is 10 percent and the expected annual cash flows are as follows: Year 0 1 2 3 4 Project A - RM 12,000 RM 6,500 RM 3,000 RM 3,000 RM 2,000 Required: (a) Calculate the Net Present Value (NPV) (b) Calculate the internal rate of return. (c) (d) How do we decide if a capital investment project should be accepted or rejected? Calculate the Adjusted Present Value (APV), if the firm finances the project with RM8,000 of debt at 7% and the tax rate is 45%.