8. The new director of special events at a large university has decided to completely revamp gradu- ation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances, as shown in the table. Gradua- tion day is 16 weeks from now. Assuming the project begins now, what is the probability that the project will be completed before a. Graduation time? b. The end of week 15? c. The end of week 132 Expected Duration Path (weeks) Variance 10 1.21 2.00 с A B 8 mo>> 12 1.00 15 2.89 1.44 14