Question 12 Not yet answered Points out of 4.00 F Flag question Question 13. Not yet answered Points out of 5.00 Flag qu
Question 12 Not yet answered Points out of 4.00 F Flag question Question 13. Not yet answered Points out of 5.00 Flag question The table is for the next two Questions. Activity Activity Time (weeks) A 13 B C Immediate Predecessor(s) none A B D 15 B E 4 C F 3 D G 2 E, F Construct a network diagram using AON notation. (this is not a Question.) Then calculate the completion time for the project. Identify the critical path. GCBDA EF 4 2 weeks