A system adopts a Round Robin scheduling with a Time Quantum=6 wherein the Arrival Times and Burst Times for each proces

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A system adopts a Round Robin scheduling with a Time Quantum=6 wherein the Arrival Times and Burst Times for each proces

Post by answerhappygod »

A system adopts a Round Robin scheduling with a Time Quantum=6
wherein the Arrival Times and Burst Times for each process have
been shown in the table below. In a recorded time span, the system
has five processes, P1, P2, P3, P4 and P5 as shown in the following
table. Process ID P1 P2 P3 P4 P5 Arrival Time t=0 t=10 t=20 t=30
t=40 Burst Time 24 16 28 10 20)

At time t=16, the process running will ask for some 1/O. The I/O
operation takes 20 time units to complete. At time t=32, the
process running will ask for some I/O. The 1/0 operation takes 16
time units to complete.

Draw a Gantt Chart (Timing Diagram) for the above data. 2)
Calculate the Waiting Time for Process P2 and P3 only. 3) Calculate
the Response Time for Process P4 and P5 only. 4) Calculate the Turn
Around Time for Process P1 and P2 only. (13 points) (4 points) (4
points) (4 points)